MA-MAC-Boiler/Chiller Replacement
Project Number
00-09248.00
DGS Number
800-311
Project Status
Trade/Bid Packages
Campus
Mont Alto
Project Stage
Out to Bid
Project Description
HVAC work is needed to replace the existing boiler in the Multipurpose Activities Center at the Penn State Mont Alto Campus.
Bid Due Date and Time
Additional Information
Bids will be received electronically only through the e-Builder Bid Portal. Bids in any other format will not be accepted.
This bid opening will be public via Zoom Webinar as a project delegated to Penn State by the Pennsylvania Department of General Services (DGS).
Capital Project (>$10M)
No
Penn State Project Leader Name, Email
Package Number | Pre-Bid Date/Time | Pre-Bid Meeting | Bid Date/Time | Awarded To | Document | |
---|---|---|---|---|---|---|
01 | HVAC | Recommended but not Mandatory | Bid Tab | |||
02 | Electrical | Recommended but not Mandatory | Bid Tab | |||
03 | HVAC - Chiller | Recommended but not Mandatory | ||||
04 | Plumbing - Chiller | Recommended but not Mandatory | ||||
05 | Electrical - Chiller | Recommended but not Mandatory |