UP-Thompson Hall Improvements
The Thompson Hall Improvement project includes bathroom renovations and the addition of additional bedrooms. Additional scope includes the renovation of the community lounge/kitchen, the renovation of existing single rooms with private bathrooms, the conversion of an apartment into an emergency-use bedroom, the renovation of the building's laundry area, and upgrades to staff spaces.
Attendees should park in the surrounding decks or in permitted parking areas, as applicable. Attendees should meet in the parking lot adjacent to Thompson and Jordan Hall 10 minutes prior to sign-in.
Prequalification forms are available in the frontend specifications.
Bid documents are expected to be released on Monday, August 31st, for public bid via Building Connected. Interested bidders can access the link through the Poole Anderson website at https://www.pooleanderson.com/subcontractors/.
| Package Number | Package Name | Pre-Bid Date/Time | Pre-Bid Meeting | Bid Date/Time | Awarded To | Document |
|---|---|---|---|---|---|---|
| 01 | Select Demo and Abatement | Mandatory | ||||
| 02 | Misc Metals | Recommended but not Mandatory | ||||
| 03 | General Trades | Recommended but not Mandatory | ||||
| 04 | Millwork and Casework | Recommended but not Mandatory | ||||
| 05 | Sprayed Insulation | Recommended but not Mandatory | ||||
| 06 | Doors, Frames, and Hardware | Recommended but not Mandatory | ||||
| 07 | Aluminum, Glass and Glazing | Recommended but not Mandatory | ||||
| 08 | Walls and Ceilings | Recommended but not Mandatory | ||||
| 09 | Wall and Floor Tile | Recommended but not Mandatory | ||||
| 10 | Resilient and Carpet Flooring | Recommended but not Mandatory | ||||
| 11 | Painting and Wallcoverings | Recommended but not Mandatory | ||||
| 12 | Fire Protection | Recommended but not Mandatory | ||||
| 13 | Plumbing | Recommended but not Mandatory | ||||
| 14 | HVAC | Recommended but not Mandatory | ||||
| 15 | Lighting and Electrical | Recommended but not Mandatory |