UP-Pollock Halls Phase 3C
Project Number
00-10700.00
Project Status
Trade/Bid Packages
Campus
University Park
Project Description
Full renovation of Porter and Shunk Halls.
Penn State Project Leader Name, Email
Project Stage for Trade/Bid Package Information
Out to Bid
Prequalification
Prequalification is not required for bidding but will be required for contracting.
Additional Information
Bid through Building Connected
Bid Due Date and Time
| Package Number | Package Name | Pre-Bid Date/Time | Pre-Bid Meeting | Bid Date/Time | Awarded To | Document |
|---|---|---|---|---|---|---|
| 002 | Demolition | |||||
| 003B | Building Concrete | |||||
| 003E | Site Concrete | |||||
| 004 | Masonry | |||||
| 005 | Structural Steel | |||||
| 006 | FRP, Scanning, & Concrete Infills | |||||
| 007 | Elevators | |||||
| 008 | Roofing | |||||
| 009 | Glass and Glazing | |||||
| 010 | Finish Carpentry & Millwork | |||||
| 011 | Drywall & ACT | |||||
| 012 | Specialties | |||||
| 013 | Painting | |||||
| 014 | Fireproofing | |||||
| 015 | Doors, Frames, & Hardware | |||||
| 016 | Window Treatments | |||||
| 017 | Flooring | |||||
| 018 | Tile | |||||
| 019 | Music Room | |||||
| 020 | Mechanical | |||||
| 021 | Electrical | |||||
| 022 | Plumbing | |||||
| 023 | Fire Protection | |||||
| 024 | Earthwork, Site Utilities | |||||
| 025 | Landscape | |||||
| 026 | Final Cleaning | |||||
| 027 | Temp Fence | |||||
| 028 | Exterior Facade | |||||
| 029 | Metal Panels | |||||
| 001 | Abatement | Mandatory |