UP-Hamilton Bathrooms Phase II

Project Number
00-07111.00
Project Status
Trade/Bid Packages
Complete - Trade/Bid Packages
Campus
University Park
Project Stage
Out to Bid
Project Description

Renovation of three bathroom stacks in Hamilton Hall.
Phase 1 — Stack B (Completed)
Phase 2 — Stack D (Ongoing)
Phase 3 — Stack A (Bidding)
Phase 4 — Stack D (Forthcoming)

Penn State Project Leader Name, Email
Architect/ Engineer and Design Build Selection
Capital Project (>$10M)
No
Professional Consultant
Company Name
Hoffman Leakey Architects LLC
Contact Name
Michael Leakey
Phone
(814) 466-7811
Construction Manager Selection and Other Services
CM Firm
Company Name
Poole Anderson Construction
Contact Name
Eli Manges
Phone
(814) 272-4534
Trade/Bid Package Information
Project Stage for Trade/Bid Package Information
Out to Bid
Prequalification

Poole Anderson requests that all bidders fill out a prequalification form prior to formal contracts. The Prequal Form can be found in the Appendices of the front end documents posted on e-Builder as well as in the FILES tab on Building Connected. Interested trade partners can also reach out direct and the prequalification form can be emailed.

Additional Information

The bid process will be handled through Building Connected. Access to the bid invitation and bid documents can be accessed free of charge through the Building Connected link (https://www.buildingconnected.com/). Access can also be found on the Poole Anderson website under the Subcontractors tab (https://www.pooleanderson.com/subcontractors/).

Bid Due Date and Time
Package Number Package Name Pre-Bid Date/Time Pre-Bid Meeting Bid Date/Time Awarded To Document
01 Abatement and Selective Demolition Mandatory Plymouth Environmental
02 Plumbing Make Safe Mandatory Allied Mechanical
03 HVAC Make Safe Mandatory Allied Mechanical
04 Sprinkler Make Safe and Modify Mandatory Moore Fire Protection
05 Lighting/Electrical Make Safe Mandatory Tri M Group
07 Final Cleaning Recommended but not Mandatory
08 General Trades Recommended but not Mandatory
09 Millwork and Casework Recommended but not Mandatory
10 Doors, Frames, and Hardware Recommended but not Mandatory
11 Walls and Ceilings Recommended but not Mandatory
12 Wall and Floor Tile Recommended but not Mandatory
13 Resilient Flooring Recommended but not Mandatory
14 Painting and Wall Coverings Recommended but not Mandatory
15 Fire Protection Recommended but not Mandatory
16 Plumbing Recommended but not Mandatory
17 HVAC Recommended but not Mandatory
18 Lighting and Electrical Recommended but not Mandatory
3.01 Final Cleaning Recommended but not Mandatory
3.02 Select Demolition and Abatement Mandatory
3.03 MIsc Metals Recommended but not Mandatory
3.04 General Trades Recommended but not Mandatory
3.05 Millwork and Casework Recommended but not Mandatory
3.06 Doors, Frames and Hardware Recommended but not Mandatory
3.07 Walls and Ceilings Recommended but not Mandatory
3.08 Wall and Floor Tile Recommended but not Mandatory
3.09 Resilient and Carpet Flooring Recommended but not Mandatory
3.10 Painting and Wall Coverings Recommended but not Mandatory
3.11 Fire Protection Recommended but not Mandatory
3.12 Plumbing Recommended but not Mandatory
3.13 HVAC Recommended but not Mandatory
3.14 Lighting and Electrical Recommended but not Mandatory