UP-Hamilton Bathrooms Phase II
Renovation of three bathroom stacks in Hamilton Hall.
Phase 1 — Stack B (Completed)
Phase 2 — Stack D (Ongoing)
Phase 3 — Stack A (Bidding)
Phase 4 — Stack D (Forthcoming)
Poole Anderson requests that all bidders fill out a prequalification form prior to formal contracts. The Prequal Form can be found in the Appendices of the front end documents posted on e-Builder as well as in the FILES tab on Building Connected. Interested trade partners can also reach out direct and the prequalification form can be emailed.
The bid process will be handled through Building Connected. Access to the bid invitation and bid documents can be accessed free of charge through the Building Connected link (https://www.buildingconnected.com/). Access can also be found on the Poole Anderson website under the Subcontractors tab (https://www.pooleanderson.com/subcontractors/).
Package Number | Package Name | Pre-Bid Date/Time | Pre-Bid Meeting | Bid Date/Time | Awarded To | Document |
---|---|---|---|---|---|---|
01 | Abatement and Selective Demolition | Mandatory | Plymouth Environmental | |||
02 | Plumbing Make Safe | Mandatory | Allied Mechanical | |||
03 | HVAC Make Safe | Mandatory | Allied Mechanical | |||
04 | Sprinkler Make Safe and Modify | Mandatory | Moore Fire Protection | |||
05 | Lighting/Electrical Make Safe | Mandatory | Tri M Group | |||
07 | Final Cleaning | Recommended but not Mandatory | ||||
08 | General Trades | Recommended but not Mandatory | ||||
09 | Millwork and Casework | Recommended but not Mandatory | ||||
10 | Doors, Frames, and Hardware | Recommended but not Mandatory | ||||
11 | Walls and Ceilings | Recommended but not Mandatory | ||||
12 | Wall and Floor Tile | Recommended but not Mandatory | ||||
13 | Resilient Flooring | Recommended but not Mandatory | ||||
14 | Painting and Wall Coverings | Recommended but not Mandatory | ||||
15 | Fire Protection | Recommended but not Mandatory | ||||
16 | Plumbing | Recommended but not Mandatory | ||||
17 | HVAC | Recommended but not Mandatory | ||||
18 | Lighting and Electrical | Recommended but not Mandatory | ||||
3.01 | Final Cleaning | Recommended but not Mandatory | ||||
3.02 | Select Demolition and Abatement | Mandatory | ||||
3.03 | MIsc Metals | Recommended but not Mandatory | ||||
3.04 | General Trades | Recommended but not Mandatory | ||||
3.05 | Millwork and Casework | Recommended but not Mandatory | ||||
3.06 | Doors, Frames and Hardware | Recommended but not Mandatory | ||||
3.07 | Walls and Ceilings | Recommended but not Mandatory | ||||
3.08 | Wall and Floor Tile | Recommended but not Mandatory | ||||
3.09 | Resilient and Carpet Flooring | Recommended but not Mandatory | ||||
3.10 | Painting and Wall Coverings | Recommended but not Mandatory | ||||
3.11 | Fire Protection | Recommended but not Mandatory | ||||
3.12 | Plumbing | Recommended but not Mandatory | ||||
3.13 | HVAC | Recommended but not Mandatory | ||||
3.14 | Lighting and Electrical | Recommended but not Mandatory |