Chilled Water Piping Installation in Walker Tunnel
Project Number:
00-07064.00
Campus:
Project Description:
Mechanical scope of work includes installation of new chilled water piping and modifications to existing chilled water piping inside Walker Tunnel. Modifications to existing low pressure steam and condensate piping in one portion of the Tunnel. New insulation on all piping (see phasing details within scope of work).
Electrical scope of work includes the installation of new LED light fixtures, conduit, and wiring inside Walker Tunnel.
PSU Project Leader:
Bid Date and Time:
Thursday, August 20, 2020 - 3:00pm
Prequalification:
Bidders need to be Pre-qualified with The Pennsylvania State University.
Additional Information:
- Confirm Intent to Bid by Close of Business on Friday, 8/7/20.
- Mandatory Virtual Pre-Bid on Monday, 8/10/2020.
- Mandatory Walk-through on-site on Wednesday, 8/12/2020. Coordinate time between 1:00 p.m. and 5:00 p.m. with PSU. Details about this will be discussed during the virtual pre-bid meeting.