Section 23 21 23
Replace current section in its entirety to include new requirements of general design and installation.
Section was updated primarily for the following reasons:
- To develop and document General Owner Requirements in order to define basic desgin intent and selection criteria.
- Goal - to provide guidelines to promote and achieve efficiency and reliability throughout entire operating range.
- To update the Equipment Requirements for the technical details of pump construction.
- Goal - to improve specifications in order to achieve better and more serviceable pumps.
- To develop and document the Execution (Installation, Operation, and Start-up/Commissioning) Requirements.
- Goal - to achieve better installations, better operating efficiency and longer life out of pump systems.
- Note the following special points:
- Manual balancing valves and Triple Duty Valves are not to be used at pump discharges.
- Pump leveling and base grouting requirements.
- Vibration Control and Final Alignment Requiprements.
- Impeller trimming requirements more stringent than ASHRAE 90.1.