Sections

Division 33

33 00 00 UTILITIES

33 01 00 GENERAL REQUIREMENTS AND OWNER INTENT

.01 General
  1. All new construction or renovation projects which necessitate modification of or an addition to existing utility systems must be coordinated with and approved by Engineering Services in the Utilities Division of OPP.
  2. Instructions to Professionals
    1. Once-thru cooling using potable water is not permitted on any equipment.
    2. Planning Modules (PADEP Chapter 71) are required for any project when new flows are projected.  The Professional shall obtain the standard planning module documents from PADER and complete them for processing.  Documents will be submitted to Engineering Services for review and approval.  If the project will discharge to a PSU Waste Water Treatment Plant, it requires a letter of documentation by PSU that the conveyance and treatment facilities have adequate capacity to accept the additional sewage flows generated by the specific project. 
      • Following approval of Engineering Services, the Project Manager shall direct submission to the appropriate municipality with the proper request for resolution and submittal to PADER.
      • Approval by PADER is required prior to commencement of project construction.
    3. The Utility Demand and Consumption form (See 00 51 00 Miscellaneous Forms) shall be completed by the Professional for every project.  The information will be used to evaluate the impact on the existing distribution systems, and to request operating funds for the facility.  The consumption data should be estimated as accurately as possible, and provided with the final design submission.
    4. All piped utilities (water, storm, and sanitary) serving more than one building shall be designed to be fully accessible for maintenance.  These utilities shall not be designed to be located under buildings.
    5. All piped utilities shall include a continuous #10 wire installed with the utility line to be used for future locates. 
      1. Wires shall extend above grade and shall terminate at a building wall, the top of catch basins or manholes, or similar, visible locations.  Precise location of termination shall be approved by Engineering Services.
      2. Tracer wiring shall be installed with all utility lines, regardless of material or service.  Where multiple electrical conduits are installed in a single concrete ductbank, only one tracer wire shall be installed per ductbank.
    6. Supporting calculations shall be provided for all designs and studies to the Office of Physical Plant at their request.  The professional shall keep all information available for a period of no less than five (5) years from the project’s completion.
    7. All plans must contain a note on the cover sheet indicating that all new utilities must be “as-built” surveyed and the surveys must be provided digitally in AutoCAD format to the University.
  3. Instructions to Contractors
    1. Utilities serving existing buildings, installations, or facilities shall not be interrupted until the Contractor has made the necessary arrangements with, and has received approval from, the University.
    2. In the event that interruption of any existing utility service is necessary, the responsible Contractor shall be required to make all the arrangements for shutdown and start-up of such service with the University representative.
    3. University crews must be used to shut down and start up all University owned services which require interruption for temporary or permanent connections.
    4. All planned interruptions to University services must be scheduled two (2) weeks in advance and the work will generally be done outside of normal working hours.
    5. The Contractor shall provide a certification that all plumbing materials are lead-free and meet the requirements of the Pennsylvania Plumbing System and Lead Ban Notification Act where the building will be serviced by a University water system (University Park, Mont Alto, and Wilkes-Barre Campuses).  This certification shall be signed by the Contractor, notarized, and submitted to the University before the water service is turned on.  Return completed form (see Figure 15G-I) to Director, Utilities Division, Office of Physical Plant.
    6. The consultant must provide digital (AutoCAD) as-built surveys of the all new utilities to the University.  Red line mark-ups are not acceptable.
.02 Temporary Utility Service

See Section F, General Conduct of the Work and Special Requirements.

33 10 00 WATER UTILITIES

.01 Water
  1. Distribution Systems
    1. Building service sizing, including meters, valves, etc., shall be performed by the Engineer of Record.
    2. Waterlines
      1. Waterlines three inches in diameter and greater shall be ductile iron pipe meeting all requirements of ANSI/AWWA C110/A21.10 and ANSI/AWWA C111/A21.11.  The class for ductile iron pipe shall be thickness Class 52.  Fittings shall be Class 350#, ductile iron compact or full body mechanical joint fittings.  All ductile iron pipe and fittings shall be double cement lined and coated outside with a bituminous seal coat all according to ANSI/AWWA C104/A21.4 and ANSI/AWWA C151/A21.51 respectively.  All pipe shall be push-on joint type with gasket conforming to ANSI/AWWA C111/A21.11 and shall be American Pipe Flex-Ring/Field-Loc, Fast-Grip gasket or equal as approved by Engineering Services.
      2. Waterlines smaller than three inches in diameter shall be copper service tubing conforming to the requirements of ASTM Designation B88, Type K, heavy wall, soft temper.  Copper service lines shall have grip joint-type fittings.
      3. Mechanical joint restraint shall be accomplished by the utilization of joint restraints ("Megalugs") with adequate concrete thrust blocks as approved by both the National Board of Fire Underwriters "Standard for Outside Protection" and Penn State Engineering Services.
      4. Provide air release/vacuum break at all high points in new distribution piping.  Refer to Detail 15G-E.  Details are not yet available in WEB-based manual.
      5. All water lines shall be designed to be a minimum of 4 feet and a maximum of 8 feet below finished grade.  The trench shall be backfilled on the bottom and sides of the pipe to a height of one foot above the top of the pipe with crushed stone dust.  The remaining backfill material shall be earth, free of wood, ashes and other debris, but may contain rock pieces not larger than one cubic foot in volume, but consisting of not more than twenty-five percent rock by volume.  No other material shall be used as backfill.
      6. Provide adequate thrust blocks.
    3. Water Meters
      1. The water flow to each building shall be metered with a cyclometer counter giving a direct reading in gallons.  All meters larger than 2" shall be compound meters.  A touch read remote transmitter shall be provided and the counter located in an approved location. 
      2. Meters shall conform to AWWA Standard.  A full-size bypass shall be provided around the meter to allow for servicing.  Refer to Detail 15G-G.  Details are not yet available in WEB-based manual.  Provide a meter manufacturer recommended strainer with each meter.
        1. At locations served by the University Park Utility Water Services system, meter and associated strainer shall be provided by Utility Services for installation by the contractor.
        2. At all other locations, meter manufacturer shall be Neptune, unless otherwise required by the local water authority. 
    4. Valves - Underground
      1. Gate valves shall be manufactured in accordance with ANSI/AWWA C509.  The type shall be RESILIENT SEATED and shall have a nonrising stem.  THE DIRECTION TO OPEN SHALL BE COUNTERCLOCKWISE.  The operating nut shall be two inches square.  Valves shall have ends suitable for use with mechanical joint pipe.  Exterior of valve shall be coated with bituminous seal coat.
      2. Valve boxes shall be cast iron of the three piece screw type installed over the bonnet and operating nut, and of sufficient length to reach the surface of the ground but not extend above the ground surface.  The word "water" shall be cast in valve box lid.
    5. Constant Pressure Pumps
  2. System Tests and Disinfection
    1. Testing shall conform to AWWA C-600.
    2. Disinfection shall conform to AWWA C-651.  Contractor shall retain the services of a PaDEP certified water testing laboratory to sample and test the potable water system.  All test results shall be provided to Utility Services prior to activation of services by Utility Services.
    3. Meter and backflow prevention device shall be installed and inspected by Utility Services prior to service activation.
  3. Fire Hydrants
    1. At University Park Campus, fire hydrants shall have National Standard threads.  Fire hydrants shall conform to AWWA C-502.  Fire hydrants shall have 2-2 1/2" hose outlets and one 4 1/2" pumper connection.  Hydrants shall be American Darling No. B-62-B-5 fire hydrants with traffic feature, or other as approved by Utility Services.
    2. At locations other than University Park Campus, coordinate threads and outlet size with fire department serving that location. Hydrants shall be American Darling No. B-62-B-5 fire hydrants with traffic feature, or other as approved by Utility Services.
    3. Refer to Detail 15G-F.  Details are not yet available in WEB-based manual.
    4. At the University Park Campus, fire hydrant flow for existing hydrants may be available from Engineering Services.
  4. Backflow Prevention
    1. No water service connection shall be installed or maintained to or at any building where actual or potential cross-connections to the system would result, unless such actual or potential cross-connections are abated or controlled to the satisfaction of Engineering Services.
    2. No connection shall be installed or maintained whereby water from an auxiliary water supply may enter the University water system unless such auxiliary water supply and the method of connection and use of such supply shall have been approved by Engineering Services.
    3. An approved backflow prevention device shall be installed prior to the first branch line leading off each service line to a building water system.
    4. An approved double check or reduced pressure zone backflow prevention device shall be installed on each service line to a building water system.  Type of backflow prevention device shall be determined by Engineering Services.  Backflow prevention devices shall be installed at a location and in a manner approved by the Engineering Services and shall be installed by a person properly qualified.  At University Park, Apollo brand backflow preventers shall be furnished by Utility Services for installation by the contractor on the potable water service. Reduced pressure backflow preventers shall not be located in pits or other areas that can fill with water unless previously approved by Penn State Engineering Services.  Backflow prevention devices shall be located on the building side of the water meter, as close to the meter as is reasonably practical and prior to any other connection.
    5. An ASSE certified double check valve shall be installed on each fire service.  Fire service backflow preventers shall NOT be furnished by Utility Services, regardless of location.
  5. Booster Pumps
    1. Where a booster pump has been installed on the service line to or within any building, such pump shall be equipped with a low pressure cut-off device designed to shut off the booster pump when the pressure in the service line on the suction side of the pump drops to ten pounds per square inch gage or less for a period of 30 seconds or longer.
  6. Operation and Connection to Existing Waterlines
    1. The operation of all existing water valves and hydrants shall be done only by University water system operators.  The Contractor and any other personnel are expressly forbidden from operating the water system components.
    2. At University Park, all connections to existing waterlines shall be done by the University.  These connections shall be done as follows:  The Contractor shall provide all required fittings, excavate a pit of sufficient size to install the tapping machine, provide equipment to place and remove the tapping machine, backfill the excavation after the tap is made, restore the surface area, and pay the University a fee for the tap.  The fee shall be as determined by the Manager, Utility Services.  The University will provide the tapping machine and perform the tapping of the existing waterline. 
    3. At all Penn State locations other than University Park, connections to existing waterlines shall be done by the contractor, but only in the presence of PSU Office of Physical Plant staff.
  7. Temporary Water Service
    1. Temporary service is defined as a water service provided for events, food vending, construction, or maintenance supplied from a building or hydrant using temporary piping for 30 days or less.  Nonpermanent service (greater than 30 days) will be addressed by the Office of Physical Plant, Water Systems, on a case-by-case basis.
    2. The Pennsylvania State University, Office of Water Systems, will provide customer hook-up to an existing building source such as hose bibbs, including a backflow preventer, and water meter.
    3. The University will ensure proper disinfection by sampling at the existing hose bibb for chlorine residual and coliform bacteria prior to customer use of the water.
    4. It is the customer's responsibility to ensure that proper disinfection continues from the existing hose bibb to their equipment and to the consumer.  The University will provide a procedure with recommendations to the customer to ensure proper disinfection.  (See Fact Sheet.)
    5. The temporary tap and sampling costs will be the responsibility of the customer.

33 20 00 WELLS

  1. At University Park, the University supplies the University Park Campus, the Research Park, and Mount Nittany hospital drinking water from deep wells located on PSU property near campus. These wells produce very high quality water at pumping rates from 200gpm to 1200 gpm per well. The University considers these wells a valuable resource that must be protected.  In addition, the University Park water withdrawal is regulated by the Susquehanna River Basin Commission and its rules and regulations.  All well drilling activity shall comply with SRBC regulations.
  2. In keeping with its focus on environmental stewardship, the University considers groundwater a valuable resource that must be protected at all locations, not just those where groundwater is used for potable water services.
  3. Any project that is considering geothermal, production, test or monitoring wells shall meet the following:
    1. The Project shall retain the University’s registered geologist during the early planning phase to determine the feasibility of installing geothermal wells, and set preliminary limitations on wells drilled within the project area.
    2. If geo-thermal wells are feasible, the Project can retain another registered geologist to provide a Drilling Plan.
    3. No drilling shall be done before this Plan is approved by Engineering Services.
    4. All drilling shall be under the direction of a registered professional geologist.
    5. The Plan shall include but not limited to the following as a minimum:
      1. Details of the exploratory and finished wells.
        1. Number proposed
        2. Proposed location
        3. Proposed depth
        4. Proposed construction: The Plan must address how the drilling contractor will deal with conditions such as lost circulation during drilling and loss of grout during the grouting operation.
        5. Material used in the construction and chemical composition of all material used in the well.
      2. Name and contact information for the drilling contractor.
      3. Proposed dates of drilling.
      4. Name and contact information of the geologist representative that will be on site during drilling.
      5. All open drill holes shall be equipped with a locking cap.
      6. Abandonment Plan for test wells in the event geothermal wells are deemed to be infeasible.
    6. Upon completion of the drilling, drilling logs for each well shall be provided to Engineering Services. Electronic copies are encouraged. The drilling log shall include the following:  description of geologic material encountered (limestone, dolomite, etc.), depth to competent bedrock, static water level, depth and flow rate of water bearing zones, depth interval of voids or significant fracture zones, depth interval and diameter of boreholes, casings (both inside and outside).
    7. If an exploratory/test well is completed, the results shall be provided to Engineering Services along with any changes to the approved Drilling Plan resulting from data collected from the test well.

33 30 00 SANITARY SEWERAGE UTILITIES

.01 Sanitary Systems
  1. Collection Systems
    1. Provide manhole at change of directions.  Note:  See Manhole Details 15G-A and 15G-B.  Details are not yet available in WEB-based manual.
    2. Sanitary sewer lines shall be either PVC, vitrified clay, or ductile iron.  All pipe shall have a premium watertight joint.
    3. Minimum size storm and sanitary lines shall be six (6) inch.
    4. All storm and sanitary lines shall be a minimum of 4 feet below grade and backfilled on the bottom and sides of the pipe to a height of one foot above the top of the pipe with PennDOT 2A Stone.  The remaining backfill material shall be earth, free of wood, ashes and other debris, but may contain rock pieces not larger than one cubic foot in volume, but consisting of not more than twenty-five percent rock by volume.  No other material shall be used as backfill.
    5. All sanitary manholes shall be tested to establish no infiltration using either a hydraulic or pneumatic test.  All sanitary sewer lines shall be tested to establish no infiltration using a low pressure air test.  Coordinate with Engineering Services.
    6. Provide clean-outs on building sanitary sewer laterals at changes in direction and at maximum intervals of 150 feet.
  2. House Traps
    1. House traps are not required unless a specific request is made by the codes official.
  3. Manholes
    1. Sanitary Manholes.
      1. Manholes shall be provided at changes in direction.
      2. Manholes shall be fitted with non-locking type or locking type (as required by service and indicated on drawings) heavy frame and cover.  The type of service shall be cast in each cover in three (3) inch high letters.
      3. Provide manholes with cast-in-place rungs made of aluminum conforming to ASTM B221, alloy 6061T-6.  Coat the embedded ends of aluminum rungs with two coats of bituminous paint.  Space rungs 12" center to center.  Steps shall be 12" wide with five (5) inch projection from the wall and 4 1/2" projection into the wall.
      4. Manholes shall be reinforced precast concrete and conform to ASTM C-478.  Provide suitable rubber gasketed joints which meet ASTM C443 between sections.  Manhole bases shall be cast-in-place concrete.  The top section of the manhole shall be of the eccentric cover type so that manhole steps form a straight ladder, for manholes 5'-0" and deeper.  Openings required that are not cast in the manholes must be machine core bored.
      5. Provide invert channels of cast-in-place 3500 psi concrete.  The channel shall be smooth and accurately shaped to conform to the inside surfaces of the incoming and outgoing pipes.
      6. Provide outside drop connections where the difference between the inflow and outflow elevation exceeds 2'0".  Encase the drop pipe and fittings in 3,500 psi concrete.
      7. Joining of pipes to manholes shall be made thru rubber gaskets cast integrally in the manhole wall and located as required.  Joints shall meet the requirements of ASTM C443 and ASTM C425.
      8. Refer to Details 15G-A and 15G-B (15G changed to Division 33).  Details are not yet available in WEB-based manual.
  4. Oil/Water Separators
    1. Oil/water separators shall be used wherever mandated by Federal, State, local, or University criteria.  Under no circumstance shall any oil/water separator be installed without being reviewed by Engineering Services.
    2. The use of enzymes or chemicals shall not be permitted without the approval of the required regulatory authority.
    3. Oil/water separators shall discharge to the sanitary sewer.
    4. Operations and Maintenance (O&M) manual shall be provided to the University for any Oil/water separator.  The O&M manual will also include design assumptions used, sizing computations, and recommended cleaning schedule.
    5. Refer to section 33 56 00.

33 40 00 STORM DRAINAGE UTILITIES

Document

 Version 
Date

Description
Fox Hollow Drainage Basin Stormwater Management Design Manual        

February 2003 

This manual includes technical standards and criteria that apply to the development of a Storm Water Management Plan (SWMP) for all land development activities within the University Park Campus Fox Hollow Drainage Basin. All Projects that impact the land areas or drain to the Fox Hollow Drainage Basin (area as defined in this manual) shall conform to the requirements listed herein.
Penn State Stormwater Management Summary

June 2007

All projects that have stormwater must submit this form completed to Engineering Services.
Penn State Stormwater Operations and Maintenance Summary Sheet

June 2007

 All projects that have stormwater BMPs (structural and non-structural) must submit this form completed to Engineering Services.
Penn State Stormwater Green Roof Summary Sheet

 June 2007

All projects that have green roofs must submit this form completed to Engineering Services.
.01 Stormwater Systems
  1. Stormwater Management
    1. All projects shall include a stormwater management plan that conforms to the most recent local stormwater management ordinance.  Projects at University Park located within the Fox Hollow Drainage Basin shall conform to the Fox Hollow Drainage Basin Stormwater Management Design Manual.
    2. Recommended Practices
      • The University promotes foremost the use of conservation design practices that preserve and use natural critical hydrologic areas, including, but not limited to, floodplains, wetlands, streams, minor drainageways, natural recharge areas, carbonate closed depressions and sinkholes.  It also promotes the use and application of sound science in our stormwater management practices and does not believe that any BMP or Low Impact Development (LID) method can be used anywhere, or that we can engineer replacements to complex natural hydrologic areas. Therefore, site designers shall make every effort to preserve these areas, and any disturbance is only permitted at the approval of OPP Engineering Services.
      • Adequate treatment must be accomplished prior to stormwater runoff being injected into an engineered infiltration BMP or areas where infiltrated runoff can rapidly bypass the soils and enter fractures or the groundwater. Water quality pretreatment facilities must be visible and accessible to provide a means to monitor their efficiency, and replace if necessary in case of failure.  Every effort should be made to insure that the quality of stormwater that is to be artificially recharged is of equal or better quality than the existing groundwater.  If sinkholes or rapid infiltration does occur, limited water quality impacts may occur if the water is of high quality.
      • Construction practices must be utilized so as to minimize the compaction of existing soils.  In addition, a) soil at grade should be managed and b) vegetative cover and organic amendments should be utilized to enhance the restoration of infiltration capacity of disturbed soils.
      • As a nationally recognized institution of higher learning, the University reserves the right to request comprehensive computations that defends a designs function above and beyond those required for regulatory approval in order to protect health, safety, and welfare.
      • The University’s recommended practices for land development activities at shall be based on a thorough understanding of the watershed, soils, geology, site density, existing conditions, and the local regulatory requirements.  Examples of recommended practices are available for the University Park Campus from Engineering Services.
    3. Supporting Documentation
      • All stormwater management final reports and plans shall be provided to Engineering Services.  In addition to the stormwater reports required by a municipality and/or PaDEP, the professional must fill out and submit the Penn State Stormwater Management Facility Summary Sheets, and the Penn State Green Roof Summary Sheets, if applicable. Final payment can be held until documentation is received.
      • Digital as-built surveys of all stormwater management facilities, including but not limited to, surface ponds, underground detention facilities, BMPs, and conveyance pipes will be provided to Engineering Services.
      • All stormwater BMPs need to be properly installed, operated, and maintained.  The professional shall provide the University with three (3) copies of all stormwater Operations and Maintenance Manuals.  Additionally, the engineer shall fill out the Penn State Stormwater Operations and Maintenance Summary Sheet, for each BMP.
    4. The use of porous (asphalt) pavement is prohibited at University Park Campus.  Porous pavement may be used at other campuses at the approval of Engineering Services.
    5. The use of structural stormwater best management practices that replace existing subsoils with inert materials or gravel are discouraged unless it can be documented that the remaining soils are stable and can renovate pollutants in the stormwater.  Stating general rules of thumb, such as there are 2ft of soil above restricting layers, are not acceptable for documentation.
  2. Collection Systems
    1. Provide manholes or inlet boxes at all horizontal or vertical changes of direction for storm drain lines.
    2. Storm drain lines shall be either corrugated metal pipe, reinforced concrete, or duel walled high density polyethylene.  If corrugated metal pipe is used, a minimum gauge of 14 shall be used and the pipe must be coated with bituminous or aluminized.  Pipe material used for pipes greater than 24” diameter shall be at the direction of Engineering Services.  All pipe shall have watertight joints.
    3. Minimum size storm drains conveyance lines shall be fifteen (15) inch, with the exception of underdrains, BMP distribution systems, properly sized roof leaders, or where the lines tie into a smaller existing downstream storm drain, which shall have a minimum size of six (6) inches.
    4. The minimum pipe slope for new storm drains shall be 0.5% (0.005ft/ft).
    5. The crowns of all storm drain lines shall be a minimum of 2 feet below grade and meet manufactures depth recommendations.  Pipes to be backfilled on the bottom and sides of the pipe to a height of one foot above the top of the pipe with PennDOT 2A stone.  The remaining backfill material shall be earth, free of wood, ashes and other debris, but may contain rock pieces not larger than one cubic foot in volume, but consisting of not more than twenty-five percent rock by volume.  No other material shall be used as backfill.
    6. Inlet boxes and appurtenances shall conform to Pennsylvania Department of Transportation Standards for Roadway Construction (RC), and Publication 408 specifications.  All yard drains, including those in landscaped areas, shall be concrete with minimum interior dimensions of 12” x 12” and shall be H20 load rated.  Yard drains located in landscaped areas with material other than concrete shall be used only when approved by Engineering Services.
    7. All storm drain structures including manholes and inlets deeper than five (5) ft shall have access steps per the PennDOT Roadway Construction standards.
    8. Some storm drains may require exfiltration testing where there are sinkholes.  Coordinate with Engineering Services.
    9. Provide clean-outs on all roof bends and at the end of BMP underdrains at a minimum.
    10. The maximum spacing between storm drain manholes or inlets shall be 300 ft.
    11. Inlet spacing on new roadways in curbed sections will be based on an allowable spread of ½ the travel lane or a maximum of 6’.
    12. All storm drain inlet grates located in travel areas or lawns to be PennDOT bicycle safe.
    13. All storm pipe or culvert outlets must have stable erosion resistant energy dissipaters.  Where hydraulically possible, outlets should use sumped pre-formed scour holes.
    14. Any new storm culvert or pipe outlet must have a concrete endwall or endsection.
    15. All storm drain hydraulic computations must be done in accordance with the Federal Highway Administration’s Urban Drainage Design Manual, Hydraulic Engineering Circular No. 22 (HEC-22).  Hydraulic grade lines for all new storm drain lines must be provide to Engineering Services on request.
    16. All new storm drains shall be designed to pass the 10-year event discharge without surcharging.  Surcharging is defined as the maximum permissible water surface elevation in a manhole or inlet one (1) ft below the top of grate elevation.
    17. Vegetated stable open channels shall be used whenever possible.  All channels greater than or equal to 10% slope shall be designed by shear stress methods.
    18. Specialized water quality inlet boxes shall not be installed without the direction and approval of Engineering Services.  Under no circumstance are systems that use replaceable filters or cartridges to be used.
    19. All manholes and inlet boxes shall have a smooth flow line channel formed of cast-in-place 3500 psi concrete for all storm drains 24 inch or larger.  The channel shall be smooth and accurately shaped to conform to the inside surfaces of the incoming and outgoing pipes.
    20. Under certain conditions, Engineering Services may request manhole covers be placed on inlet boxes.  See 33 40 00.01.C1.
    21. All subsurface detention facilities are to have access/clean out points located on each end of the facility.
    22. Sumped inlets on roads or other critical areas must have flanking inlets in the event of clogging.
    23. Under no circumstances shall surface water be directed towards a building.  All designs shall include gravity flow away from buildings in the event that inlets are clogged.
    24. The layout and design of all subsurface detention facilities shall be reviewed by Engineering Services prior to being submitted to outside review agencies.
    25. Ductile iron pipe shall be used for storm drains wherever storm drains cross steam lines closer than 3’-0”.
    26. Reinforced concrete pipe shall be used for all pipes crossing roadways.
  3. Manholes
    1. Storm Manholes
      1. Manholes shall be provided per section 33 40 00.01.B1.
      2. Manholes shall be fitted with 30” diameter non-locking type or locking type (as required by service and indicated on drawings) heavy frame and cover.  The word “STORM” shall be cast in each cover in three (3) inch high letters.
      3. Provide manholes with cast-in-place rungs made of aluminum conforming to ASTM B221, alloy 6061T-6.  Coat the embedded ends of aluminum rungs with two coats of bituminous paint.  Space rungs 12" center to center.  Steps shall be 12" wide with five (5) inch projection from the wall and 4 1/2" projection into the wall.
      4. Manholes shall be reinforced precast concrete and conform to ASTM C-478.  Provide suitable rubber gasketed joints which meet ASTM C443 between sections.  Manhole bases shall be cast-in-place concrete.  The top section of the manhole shall be of the eccentric cover type so that manhole steps form a straight ladder, for manholes 5'-0" and deeper.  Openings required that are not cast in the manholes must be machine core bored.
      5. All other manholes criteria shall conform to Pennsylvania Department of Transportation Standards for Roadway Construction (RC), and Publication 408 specifications.
  4. Oil/Water Separators
    1. Oil/water separators shall not be used for stormwater management systems except at the direction of Engineering Services.  Refer to sections 33 30 00.01.P and 33 56 00 if required.

33 50 00 FUEL DISTRIBUTION UTILITIES

.01 Gas
  1. Characteristics
    1. Underground natural gas systems at University locations may be owned and operated by either the University, or by the local natural gas distribution company.  At some locations, both conditions may exist.
    2. University owned gas piping network on University Park Campus is carried at 5 psi.  Gas is natural with heating value at 1050 btu/cu. ft.  Parts of the system owned by Columbia Gas of Pennsylvania will be carried at 35-50 psi.
    3. At all locations consult with Engineering Services for gas system ownership and procedures to be followed.
  2. Distribution Systems
    1. Piping
      1. All underground pipeline installations will be in accordance with the U.S Department of Transportation, Pipeline and Hazardous Materials Safety Administration, Pipeline Safety Regulations Part 192, Transportation of Natural and Other Gas by Pipeline: Minimum Federal Safety Standards and the International Fuel Gas Code.
      2. All contractors installing underground pipelines must be certified under the Pipeline Safety Regulations Part 192 and will provide copies of the certification to the University.
      3. The design professional will provide gas loads and pressure requirements to Engineering Services for meter and regulator sizing.  The meter and regulator will be provided by the University and the contractor will perform the installation.
      4. The piping material to be used will be determined by Engineering Services.
      5. When it is determined in a project that a pipeline owned by the local gas distribution company will be within the contract limits of that project a site utility drawing will be provided to the company for review and comment.

33 56 00 FUEL-STORAGE TANKS

.01 Underground/Aboveground Storage Tank Design
  1. EHS shall be contacted to provide guidance in the planning and design of facilities that include any new aboveground or underground storage tanks or modification/replacements of any existing tanks.  This includes tanks that are used for petroleum products and other oils as well as those used for other hazardous materials (i.e., caustic soda).  Site-specific requirements will be provided by EHS.
  2. All new fuel storage tanks shall be aboveground, unless specifically reviewed and approved by EHS.
  3. All new tanks shall have a Spill Prevention, Control, and Countermeasures (SPCC)Plan or a Preparedness, Prevention and Contingency (PPC) Plan prepared under the direction of EHS.
  4. Provide a copy of equipment, materials and installation details submittals to EHS in timely manner for review prior to installation.
  5. All tank installations shall provide complete startup and training services coordinated and scheduled well in advance with Owner’s representative(s) to attend.  Obtain certification that startup and training was completed with Owner’s representative signature(s) and submit completed certification of training to Project Manager.
.02 Aboveground Storage Tanks
  1. Provide aboveground storage tank installations in accordance with   current EPA, DEP, Department of Labor and Industry Flammable and Combustible Liquids Section (or Philadelphia or Allegheny County, where they take precedence), township/borough requirements (where applicable), NFPA, and EHS requirements.
  2. Contractor shall be required to provide the University with necessary Department of Labor and Industry Fire Safety Permit and DEP Storage Tank Registration, where applicable.
  3. All new aboveground stage tanks shall meet the appropriate UL standard.
  4. Tanks shall be set on a concrete pad to prevent the settling of the tank.  The pad shall be in accordance with the tank manufacturer’s recommendations.
  5. All aboveground storage tanks shall have secondary containment, fill drop tube, spill prevention, overfill prevention, and mechanical leak detection (electronic monitoring/alarming not required). 
  6. Any work on DEP regulated aboveground storage tanks shall be performed by DEP certified tank installer/inspector. 
  7. “No Smoking” and “Stop Motor” signs shall be posted in all fuel dispensing areas, and a “No Smoking” sign shall be displayed on the tank.  Fuel pumps and aboveground storage tanks shall be protected from vehicles with bollards.  If the tank is to be located in a trafficked area, bollards shall be installed around the tank.
    1. Bollards shall be 6” diameter standard strength steel pipes filled with concrete, with rust inhibiting coating on entire exterior surface.  Bollards shall be securely at least 3 feet into the ground, 4 feet high, 4 feet apart, set at least 2 feet from the shell of the tank.  If the tank is located in a grassed area away from travel lanes, bollards shall not be required.
  8. Contents of the tank shall be identified on the tank exterior, and all ports, vents, etc. shall be labeled.
  9. Piping (single wall) shall be run completely exposed to allow for complete visual inspection.  Otherwise if piping must be enclosed, it shall be double-wall with interstitial piping space draining back to a sump monitored by an automatic leak detection system.
.03 Underground Storage Tanks
  1. Provide underground storage tank installations in accordance with   current EPA, DEP, Department of Labor and Industry Flammable and Combustible Liquids Section (or Philadelphia or Allegheny County, where they take precedence), township/borough requirements (where applicable), NFPA, and EHS requirements.
  2. Contractor shall be required to provide the University with necessary Department of Labor and Industry Fire Safety Permit and DEP Storage Tank Registration, where applicable.
  3. All new underground storage tanks shall meet the appropriate UL standard.
  4. All underground storage tanks shall have secondary containment, fill drop tube, spill prevention, overfill prevention, and automatic electronic leak detection.  Provide audible and visual alarms annunciated in a normally occupied space.
  5. All work on DEP regulated underground storage tanks shall be performed by DEP certified tank installer/inspector.
  6. “No Smoking” and “Stop Motor” signs shall be posted in all fuel dispensing areas, and a “No Smoking” sign shall be displayed on the tank.  Fuel dispensers and pumps shall be protected from vehicles with bollards.
    1. Bollards shall be 6” diameter standard strength steel pipes filled with concrete, with rust inhibiting coating on entire exterior surface.  Bollards shall be securely at least 3 feet into the ground, 4 feet high, 4 feet apart, set at least 2 feet from the fuel dispenser or pump.
  7. Contents of the tank shall be identified on the tank fill pipe and all ports, vents, etc. shall be labeled.
  8. Piping shall be double-walled suction piping.  Interstitial space shall drain to a sump monitored by the automatic leak detection system.  Piping shall not be under positive pressure.

33 60 00 HYDRONIC AND STEAM ENERGY UTILITIES

33 61 00 HYDRONIC ENERGY DISTRIBUTION (RESERVED)

33 62 00 CAMPUS CHILLED WATER DISTRIBUTION

  1. General
    1. Much of University Park Campus is, or will be, served by a campus look chilled water system.  The chilled water system of each new building must be designed so as to be compatible with the characteristics of the campus chilled water system.
    2. Coordinating building connection requirements and proposed loads with Engineering Services, Office of Physical Plant.
  2. Details: Refer to miscellaneous typical guideline details below.  Adapt to project specific requirements.
Document Version Date
Description
SK1 (AutoCAD file)  (PDF Document)    
 February 2012 Campus chilled water system service entrance detail for buildings that do NOT require a heat exchanger.
Sequence of Operation  August 2012 Sequence of Operation for campus chilled water system service entrance detail for buildings that do NOT require a heat exchanger.
SK-2 (AutoCAD file)  (PDF Document)    
 March 2012 Campus chilled water system service entrance detail for buildings that require a heat exchanger.
Sequence of Operation  August 2012 Sequence of Operation for campus chilled water system service entrance detail for buildings that require a heat exchanger.

Isolation Valve (AutoCAD file)

   (PDF Document)

 
Details of a campus chilled water isolation valve installation.

Air Vent (AutoCAD file)

   (PDF Document)    


Detail of a campus chilled water air vent.

Sediment Blowoff (AutoCAD file

    (PDF Document)


Detail of a campus chilled water sediment blowoff.
 Building Wall Penetration (AutoCAD file)
    (PDF Document)

Detail of a campus chilled water building penetration.

33 63 00 STEAM ENERGY DISTRIBUTION

.01 Steam
  1. Characteristics at University Park Campus
    1. Low pressure steam (where available) 10-12 psi summer, 5-12 psi winter; design for 5 psi.
    2. High pressure steam (where available) 150 psi.  Pressures may fluctuate to a low of 90 psig in winter.
  2. Characteristics at other locations
    1. For characteristics at other locations, discuss with Engineering Services.
  3. Distribution Systems
    1. Steam Mains
      1. Use concrete trench design for steam, condensate, and compressed air.  For details, contact Engineering Services.  Any other types of underground piping systems must be discussed with Engineering Services.
      2. Expansion shall be taken up with expansion joints in manholes.  Expansion joints shall be Advanced Thermal Systems Type TP2, no substitutions.  Underground offsets and loops will be permitted on a case by case basis.  Design piping expansion for 250 psi.
      3. Ball joints are not normally used.  Where they must be used, because of field requirements, use the injectable packing type.  Advanced Thermal Systems Series "P2" ball joint shall be used with no substitutions.
      4. Drip stations shall be provided at all low points and every 150'-200' of run.  Refer to Division 23 22 00 for arrangement of drip station.
      5. Steam manholes require specific discussions with Engineering Services.
    2. Steam Meters
      1. Steam meters shall be selected and sized by Engineering Services. The professional shall provide building steam load to Engineering Services for steam meter sizing. 
      2. Steam meters shall be provided and installed by Utility Services.  Contractor shall install orifice flanges supplied by Utility Services.  Location of orifice flanges shall be specified by Engineering Services.  Utility Services shall install the meter transmitter.  Contractor shall provide and connect power to the transmitter from the building BAS system.
      3. The Professional shall provide for and indicate an adequate straight run of pipe on drawings for an orifice meter installation.
    3. Condensate Pumps
      1. Condensate pumps shall be duplex, not to exceed 1,800 rpm, with alternator; both pumps to come on at high level.  Discuss discharge head with the University.  Install check valves to prevent circulation through inactive pump.  See Detail 15G-C for piping at meter and condensate return pumps.
        • Discharge shall have a ball or plug valve with memory stop to provide for pump discharge pressure adjustment.
      2. Consideration shall be given to using Pressure Powered condensate pumps by Spirax/Sarco or equal, where economically justified.  Pumps shall use air for pumping where possible.
      3. See Detail 15G-D for piping connections at pressure powered condensate pumps.  Details are not yet available in WEB-based manual
      4. All steam fittings shall be ANSI Class 150 for low pressure steam and ANSI Class 300 for high pressure steam.
    4. Steam, Condensate, and Compressed Air Valves
      1. Steam valves shall be steel laminated seat zero leakage triple offset butterfly valves.  All valves to have gear operators.  Steam valves shall be ANSI Class 150 for low pressure steam and ANSI Class 300 for high pressure steam.  Valves material and construction shall be approved by Engineering Services.  Cast iron valves shall not be used.  Acceptable manufacturers are Adams, Tricentric, Zwick and Vanessa.
      2. Condensate valves 2 inch and smaller shall be stainless steel ball valves; e.g., Apollo.  Larger valves shall be high performance butterfly valves; e.g., Jamesbury or Keystone.  Valves material and construction shall be approved by Engineering Services.  Cast iron valves shall not be used. 
      3. Compressed air valves shall be stainless steel ball valves.
  4. Tests of Steam Distribution Piping
    1. New steam distribution piping systems which connect to existing hot steam lines shall be tested as follows:
      1. The new system shall be installed and the ends of the lines blanked off prior to making the connection to the existing hot line.
      2. The line shall then be hydrostatically tested as specified and thoroughly flushed out.
      3. Make final connections to existing hot lines, energize, and waste condensate.
      4. De-energize and open and clean all dirt legs and strainers.
        • (The purpose of this test is twofold:  (1) To stress line under expanded conditions prior to hydro test; and (2) To knock off and then flush out as much mill scale and debris as possible.)
.02 Air
  1. Characteristics
    1. Line pressure 60-80 pounds.  This is central plant air and is available on most of the University Park Campus.  Provide proper dryer and separator tanks with automatic blowdown piped to nearest drain, and provide refrigerated air dryer with automatic blowdown piped to nearest drain.
    2. Oil removal equipment must be provided in the building.
    3. Central air is not available at other locations.
  2. Distribution Systems
    1. Underground compressed air piping shall be fiberglass reinforced plastic (Fibercast, Centricast Plus RB-2530).  Where piping passes through manholes, convert to steel with flanges.
    2. Piping shall have a trap, with a half-inch ss ball valve and an automatic drain located at the low point where the piping enters the building.  In addition, half-inch ss ball valves with brass plugs shall be provided at all low points to bleed entrapped moisture.  Provide oil filters in the lines as needed.
    3. All underground fiberglass piping shall have a twelve gauge stranded copper tracer wire attached to the top of the pipe.
  3. System Tests
    1. All air lines shall be tested at 100 psi air pressure for a period of four (4) hours using test connections and testing equipment furnished by the Contractor.  The only permissible drop in pressure shall be that due to temperature drop.

33 70 00 ELECTRICAL UTILITIES

.01 Electric (See Division 26)

33 80 00 COMMUNICATIONS UTILITIES

.01 CCS

Refer to Division 23 09 00 and 25 00 00.

.02 Telecommunications

See Division 27.