Common Terms and Definitions
- A
- Actual Completion Date:
- Once a job has been completed and ready to be billed
- Actual Punch List Completion Date:
- The actual date when all punch list items have been completed
- A&FS:
- Administrative and Financial Services
- B
- Backlog:
- Accumulated supervisor's estimates, in man-hours, for any particular trade code
- Ballpark Estimate:
- Estimate given to a customer which is NOT a firm quote; estimate is worked to be as close to actual cost as possible; sent to customer by e-mail on standard mini-job report form
- Budget:
- The total sum of money allocated for a particular purpose or period of time or to a particular organization
- Budget Administrator:
- Individuals designated by the budget executive as being responsible for operating and controlling specific budget areas within the budget executive's administrative area. These individuals approve documents in their own name within the limits of policy FN18. The budget administrator approves transactions at the specified dollar levels and categories, affirming the need for the action and that the action is appropriate within University Policies and Guidelines
- Budget Executive:
- Individuals who are responsible to the President, Executive Vice President and Provost, or one of the senior vice presidents for a section of the budget. These individuals are normally the President's administrative staff, academic Deans, and Campus Executive Officers. The budget executive approves transactions at the upper dollar levels and specified categories, affirming the need for the action and that the action is appropriate within University Policies and Guidelines. Certain approval actions may be delegated to the budget administrator
- Building Maintenance Funding:
- Routine wear and tear activity, generally under $3,000
- C
- Capital Project:
- A work process; > $1 mil and normally requires Board of Trustees(BOT) approval; not state funded
- Change Order:
- A revision to an originally approved Project Request, E/A, Quotation, or Confirming Quotation due to a request from the originating department, or to address unforeseen conditions encountered after the project is working
- Classroom Committee, University Committee on Instructional Facilities (UCIF) -- Replaces Classroom Committee:
- The purpose of the committee is to improve the instructional environment of classrooms and other teaching facilities at the University Park Campus and the 18 Commonwealth Educational System campuses and provide consulting services for classrooms at the Behrend and Capital Colleges. They were also charged to facilitate the teaching faculty by providing classrooms that are optimal in size and condition and are equipped to meet the instructional needs of faculty and students
- CMMS:
- Computerized Maintenance Management System
- Code Compliance:
- Meeting the appropriate building codes
- Commissioning:
- Validation of a proper system operation for new construction
- Commonwealth Services:
- Non-University Park Campuses
- Completion Date:
- When all items on the punch list are done
- Computerized Maintenance Management System:
- CMMS
- Confirming Quote:
- Confirmation of a quote/price for a job after it has started
- Construction Completion Date:
- When all the construction is complete, less punch lists
- Construction Schedule:
- A formal plan for use of manpower, materials, and resources to complete a jo
- Construction:
- Working a phase of a project
- Contact Person:
- The originator of the work assignment and "person in the know"
- Contingency:
- Funds for unforeseen requirements
- Contract:
- A binding agreement between two persons or parties
- Contract Administration:
- A work unit of Design and Construction serving both University Park and Commonwealth Services
- An OPP activity administering all OPP Contracts
- CSR:
- Customer Service Representative
- Customer:
- A person or company that uses or purchases our services or products. Customers can be both "internal" and "external"
- Customer Completion Date:
- Date when customer wishes project to be done
- Customer Estimate:
- A customer's estimate of a project cost
- Customer Liaison for Projects:
- Define scope, determine desired completion date, coordinate design, obtain plan and estimates, control project budgets, coordinate access and resolve problems
- Customer Liaison for Service Calls:
- Customer relations, adjusts priorities, and resolves problems; shop supervisor
- Customer Service Representative:
- CSR
- Customer Survey Form:
- Form sent to contact person to be used to rate the entire project; sent after job has been completed and billed
- D
- Daily Schedule:
- Plan for person for the day; intra-shop schedule; done for a week at a time
- Design:
- A request made to OPP to perform a complete design for the entire project, with construction documents. This requires approval of the Facilities Coordinator (FC) . All design requests require authorization to direct bill a down payment of $2,000 or 10% of total construction
- DGS Project:
- A work process; project that receives the majority of funds from the state and normally is administered by DGS (normally > 1 mil)
- DGS:
- Department of General Services
- Direct Billing:
- An internal electronic University billing process that authorizes one department to bill another department for services that have been provided
- Direct Billing Authorization:
- A written or electronic IBIS document that outlines the requested service(s) from a University department which must include, a description of the service, the departmental charge budget and fund no., and an estimated cost, the department name and address, and the required authorized signatures
- Drawings:
- A technique of representing a plan or sketch
- E
- E/A
- Evaluation and Analysis
- Equipment:
- Asset(s) other than land or buildings
- Emergencies:
- A work process; $0 < Emergency < ? requires immediate action to prevent loss or damage to property, restore essential services or eliminate personnel hazards
- Estimate:
- Rough or approximate calculation
- Estimator:
- One who determines the cost of manpower, material and resources needed to complete a project
- Evaluation and Analysis
- A request given to OPP to complete a construction/project budget estimate for an entire job. All E/As completed by OPP are valid for 60 days. If no response is given within that time frame the project is placed on hold by OPP
- E/A
- F
- FC:
- Facilities Coordinator
- Facilities Coordinator:
- Office of Physical Plant's departmental contact for a college or department
- FC
- Facilities Resources & Planning:
- A division of OPP responsible for assigning, allocating, and reassigning building space
- Final Inspection:
- Project review before final payment
- Financial Officer:
- Individual who represents the Corporate Controller in the various budget executive areas. This position has the responsibility of assuring that budgets and expenditures are controlled, assets of the University are protected, and that all actions are in compliance with University Policies, Guidelines, and Procedures (refer to Policy FN18). In addition, the Financial Officer is responsible for ensuring the accuracy of all documents/actions through the local and central accounting and budgeting systems
- FO
- Fixed Task:
- Accounting mechanism to accumulate labor, material and equipment charges on recurring work in utilities, janitorial, and landscape
- FO:
- Financial Officer
- Forecasted Completion Date:
- An OPP date, when we wish the project to be completed
- FR&P:
- Facilities Resources & Planning
- G
- H
- I
- IC:
- Inside Construction
- Inside Construction:
- Construction done by OPP trades
- IC
- J
- Job Cost Phase:
- Job cost labor task file to do a specific project
- Job Number:
- An activity number assigned after funding and authorization(s) have been received
- K
- L
- Labor:
- Human activity that provides the goods and services in an economy
- Leader:
- Person responsible for accomplishing an objective through the work of other people
- M
- Major Maintenance Funding:
- Larger project work, generally greater than $3,000; centrally administered on 778-08 by work control; intended for repair/replacement of larger building components or systems
- Major Project:
- A work process; > $25,000 (Non Capital, Non DGS)
- Material Hold:
- A period of time for which a work assignment, or copy there of, is unavailable due to ordering, waiting for receiving and routing paperwork
- Materials:
- The elements or substances of which something is made
- Material Transfer Invoice:
- A form on which the cost of materials (and sometimes labor) can be charged to one task number and credited to another.
- Mini-Jobs:
- Jobs that are more than a work assignment and less than a project; currently, set at up to $5000; when a job would need multiple crews, this could change a work assignment to a mini-job; also, a project request to a PC could go to mini-job if under $5000
- Minor Project:
- A work process; > service call < $25000
- Mission:
- A statement defining the purpose of an organization's existence
- MTI:
- Material Transfer Invoice
- Multiple Copy Work Assignment:
- Additional copies of the same work assignment issued for a different/parallel purpose than the original, such as materials or additional trade codes working simultaneously
- N
- O
- Object Class:
- A unique number assigned to a University financial transaction identifying the type or expenditure
- OC:
- Outside Construction
- OPP:
- Office of Physical Plant
- Orientation periods:
- Familiarization and start up orientations both for OPP and the customer on equipment by the contractor
- Outside Construction:
- Construction performed by an outside concern, not OPP labor
- OC
- OT:
- Overtime
- OTC:
- Office of Telecommunications
- Overhead Tasks:
- An accounting mechanism to accumulate labor, material and equipment overhead costs (e. g. training, cleanup, shop materials, overhead materials, etc.)
- Overtime:
- Time beyond an established limit
- OT
- P
- PART
- Process Action Re-engineering Team
- PA/RT
- Process Action Re-engineering Team
- PAT
- Process Action Team
- PC:
- Project Coordinator
- Project Contact
- Phase:
- Working a specific task; i.e., to run conduit
- PL:
- Project Leader
- Planned Proactive:
- Used to designate planning activity on maintenance funded jobs or work assignments; the work activity is being done in advance of failure of equipment and has been anticipated (planned) and done in a chosen time frame
- Planning and Estimating:
- Scope verification, trade and material sequencing and detailed cost estimating
- PM:
- Project Manager
- Project Management
- Preventive Maintenance
- PM Fee:
- Project Management Fee
- PO:
- Purchase Order
- PRAG:
- Project Resource Allocation Group
- Preventive Maintenance:
- A work process; repetitive, and recurring, maintenance work, which is estimated and scheduled
- PM
- Process:
- The steps involved in accomplishing a task
- Process Action Team:
- A team of experts established to analyse and improve a process to eliminate waste in the process
- Process Action Re-engineering Team:
- A team of experts established to analyse and improve a process to eliminate waste in the process
- Professional:
- One who engages in a pursuit or activity professionally; i.e. an architect
- Project:
- A specifically formulated plan or design
- Project Contact:
- A person who initiates a project
- PC
- Project Coordinator:
- An OPP employee assisting in project management activities
- A job description in the project management area
- PC
- Project Leader:
- Coordinates all job activity and monitors costs; may be a PC, PM, operations supervisor or manager, renovations supervisor, mini-job CSR
- PL
- Project Management Fee:
- A fee or down payment required allowing the project to proceed.
- PM Fee
- Project Manager:
- An OPP employee responsible for all project activities
- A job description in the project management area
- PM
- Project Number:
- A number which identifies all project related activities
- Project Phase:
- Phases a project goes through in A&E, Design and Construction
- Project Request:
- A document to initiate some types of construction work
- Punch List:
- A list of items which must be corrected or competed before job completion
- Purchase Order:
- A project can be done with outside resources via purchase order if the anticipated work is less than $25,000; may or may not require a design; three bids generally needed; coordinated by PL; planning and estimating done by the successful bidder
- A binding document between two parties to obtain materials, parts, goods and services
- PO
- Q
- Quotation:
- A request made to OPP to complete a construction quotation for the entire project with the option given to do as a Cost (Time & Material) Quote, or a Contract (Fixed Priced) Quote. This requires approval of the Facilities Coordinator (FC). All quotations require authorization to direct bill a down payment of $2,000 or 10% of total construction/project estimate
- Quote:
- To state the current price for a commodity, a job or a project
- R
- Re-commissioning:
- Re-validation and making new construction changes depending on current usage of an existing system
- Record Drawings:
- A set of "as built" drawings
- Related Work Assignments:
- Work assignments, with different task numbers than the original, started to handle work associated with the original work assignment of for rework
- Renovations:
- To restore to a formal or better state by repairing or rebuilding
- Rework Codes:
- A three-letter code to indicate cause of rework done on a work assignment
- Risk Management:
- Insurance and legal review of a project
- S
- Scheduled Punch List Completion Date:
- The date when all punch list items must be completed
- Scheduled Start Date:
- To start a project construction
- Scoping Estimates:
- Scope is generally understood and estimate is based on square foot or unit prices using historical data; estimate is within +/-20%; no charge for the scoping estimate; scoping estimates are also done to estimate the backlog of major maintenance projects
- Service Calls:
- A work process; routine work where there will be no more than 16 hours labor and no more than 3 shops and no more than $3000 material. If the routine work exceeds any of the parameters, it will no longer be considered a service call.
- Shop Drawings:
- A set of submittals or approvals which must be approved prior to fabrication or construction
- Shop Loading:
- 1-3 month look, loads projects to specific shops, determines level of effort for work types, makes IC/OC decisions; assesses available labor
- Standing Order Number:
- Four digit budget number that customer give to CSR so mini-job can be started; a standing account with OPP's A&FS set up by departments to allow their budgets to be direct billed for services rendered
- Strategic Plan:
- The plan that defines the organization's mission, vision and strategic goals
- Supervisor's Estimate:
- Done via estimate screen; a guess in man hours, as to the work represented by a work assignment based solely on the description on the face of it
- Supervisor's Jobs:
- A job where an operations supervisor is the project leader; no formal job plan, estimate or sequence of work is prepared; generally initiated from a work assignment charged to building maintenance (770-06) that exceeds or is expected to exceed $3,000; typically no 9.5% PM fee; some originate when a repair activity is identified that is large in scope and will be done by the operations crews; nearly all are funded by major maintenance (778-08) though some may be funded by building maintenance or other sources
- T
- Task Number:
- Like phase numbers
- Telecommunications
- A science that deals with communications at a distance
- Timberline:
- Software package used for estimating; used all the time for projects; has been adapted to use on mini-jobs
- Trade Code:
- A three-digit number assigned to a particular occupational specialty
- Trades:
- Different types of architectural and construction crafts
- U
- Unplanned Reactive:
- Used to designate planning activity on maintenance funded jobs or work assignments; the work is being done in reaction to equipment that has failed and has not been anticipated (or planned); the work must occur immediately
- UR:
- Unplanned Reactive
- V
- Vision:
- A definition of where an organization aspires to be in the future
- W
- Warranty:
- A written guarantee of the integrity of a product or service
- Waste:
- The difference between the way things are now and they way they would be if everything were perfect
- WCC:
- Work Control Center
- Work Control Center:
- A division of OPP that handles work input, plans, estimates, schedules, establishes priorities, manages OPP backlogs and allocates the total resources directed to maintenance, repair, renovation, and operation of The Physical Plant
- Weekly Schedule:
- 1-2 week look; coordinate IC/OC work; inter-shop schedule; iron out scheduling conflicts
- Work Assignment Sequence:
- A number defining the expected order in which trades are assigned
- Work Coordination Duties:
- Coordinate OPP efforts to accomplish all facets of work from after assignment of service calls or following construction authorization of projects through close out, acceptance and reporting; activities requiring coordinator are: daily scheduling, daily job site access, cost control and material delivery
- Work Orders on Preventive Maintenance:
- A preventive maintenance work order is the order issued by the PMCS which directs the accomplishment of a specific PM assignment; the design team felt there was no need to change the term "work order", because it is a unique term to preventive maintenance and its meaning does not change
- XYZ